June 2011 TRIMET AG Essen placed again order
  Implementation of mechanical transfer pump including transfer launder system, crucible filling station and transfer inlet to casting furnace

 
May / June 2011 AMAG casting AG places order for 2 static calculations
  Creation of 3D modells and static calculation by means of FEM for two melting furnaces to confirm construction for capacity and weight increase of furnaces
  read more »   

 
April 2011 Speedline Austria placed order for furnace analysis
  Condition Analysis on existing melting furnace for evaluation of potetial of output increase and energy efficiency optimization. Evaluation of flue gas and fume gas system
  read more »   

 
February / March 2011 Order placed by ALERIS Recycling Duffel
  Engineering, Manufacturing, Delivery and Installation of a new flue gas system including furnace pressure control and regulation system on existing furnace line

 
February/March 2011 Engineering Order from TRIMET AG Essen
  Design and Engineering for integration of crucible filling and pre-heating station including metal transfer from stationary furnace
  read more »   

 
February 2011 Again Rio Tinto placed order about design study at IST
  Design and Engineering Study about improvement of charging methods by implementation of new charging systems
  read more »   

 
January 2011 Study Order placed to IST by Rio Tinto
  Evaluation Study about implementation of electro magnetic stirrer system on existing furnaces in Singen Plant
  read more »   

 
January 2011 Engineering Order
  Development and Design Engineering of plug system for stationary Zinc Furnace

 
Dec 2010 Successfull Hand-Over at KUMZ
  The most modern Melting and Casting Furnace Plant of Russia has been finally handed over successfully to Kamensk Uralksy Metallurgical Works plant.

 
Sep 14 - 16, 2010 ALUMINIUM ESSEN 2010
  10 years anniversary of IST - we welcome interested visitors on our stand Hall 6 Stand A 46.

 
July 2010 Start-up and Commissioning
  Actually under progress: Most modern Furnace Line at Kamensk Uralsky Plant, Russia
  read more »   

 
June 2010 New Order for IST from TRIMET
  IST just has received a new order about modification of two existing casting furnaces by installation of Porous Plug Systems. The execution time is very limited because this plant is one of the most important units for TRIMET AG Essen. For the trust in IST competence to handle this sensible project we say thank TRIMET ALUMINIUM AG Essen.

 
February / March 2010 ALUMINIUM INDIA MUMBAI
  Successfull participation on this years ALUMINIUM INDIA 2010 in Mumbai
  read more »   

 
December 2009 Great Success in Audit for IST
  In early December 2009 IST was audited by Norsk Hydro Aluminium. The result is like a Christmas Present for IST:
From this moment on IST is certified and nominated to be an "A" class supplier for Norsk Hydro Aluminium. This result in the first audit is a great success for the IST team and again proofs the high competence and engagement of IST.
We thank Norsk Hydro Aluminium for this Audit Result and we are looking forward to future Contracts.

 
April 2009 ALUSIL 2009
  Again successfull participation on the "2. International Conference and Exhibition ALUMINIUM CASTING" in Moscow on Apirl 01 - 03, 2009. IST Paper: Today’s Plant Modernisation Method – Target-Orientated Combination of Existing and New Ressources